&1 &2: Start date (&3) conflicts with finish date (&3)

Message type: E = Error

Message class: DPR_SHARED - Development Projects: Messages for Shared Objects

Message number: 220

Message text: &1 &2: Start date (&3) conflicts with finish date (&3)



What causes this issue?

The finish date (&V3&) of the project element is before its start date (
&V3&).


System Response

The system may calculate the dates incorrectly if you are using
constraint dates.


How to fix this error?

Correct the start date (&V3&) or finish date (&V3&).


Procedure for System Administrators

The system issues an error message and will not allow you to continue with this transaction until the error is resolved.