&1 &2: Actual start conflicts with fixed finish

Message type: E = Error

Message class: DPR_SHARED - Development Projects: Messages for Shared Objects

Message number: 218

Message text: &1 &2: Actual start conflicts with fixed finish



What causes this issue?

The fixed finish of the project element is before its actual start.


System Response

The system ignores the fixed finish and calculates the finish from the
actual start and the duration.


How to fix this error?

Correct the fixed finish.


Procedure for System Administrators

The system issues an error message and will not allow you to continue with this transaction until the error is resolved.


Error message extract from SAP system. Copyright SAP SE.