Duration of PPM/PDS &1 is too long
Message type: E = Error
Message class: /SAPAPO/PP_OPTIMIZER - Optimizer Messages
Message number: 236
Message text: Duration of PPM/PDS &1 is too long
What causes this issue?
The production process model (PPM) or the production data structure
(PDS) &V1& uses a resource &V2& for sequence-dependent lot-size
planning. The gross duration exceeds the length of period &V3&.
System Response
The optimization run is canceled.
How to fix this error?
Use a time bucket profile with longer periods, so that the PPM or PDS
can be scheduled without being cross-period.
Procedure for System Administrators
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.
Related Error Messages
/SAPAPO/PP_OPTIMIZER235 Product decomposition with cross-period lot-size planning is used
/SAPAPO/PP_OPTIMIZER234 Product &2 cannot be substituted by product &3
/SAPAPO/PP_OPTIMIZER237 Prod. &1 at loc. &2 is referenced by the 2 supersession chains &3 and &4
/SAPAPO/PP_OPTIMIZER238 Product &1 at location &2 is referenced by the two FFF classes &3 and &4