The inspection plan entered is not compatible with the strategy :&

Message type: E = Error

Message class: QST - Stability Study

Message number: 078

Message text: The inspection plan entered is not compatible with the strategy :&



What causes this issue?

You are trying to assign an inspection plan to a testing schedule item
(storage condition) that is not compatible with the strategy of the
testing schedule. Either the selected inspection plan does not use any
strategy, or the strategy it uses is not identical to the one that was
created for the testing schedule.


System Response

You can only assign an inspection plan to a testing schedule item for a
stability study if the inspection plan uses the same strategy as the
testing schedule.


How to fix this error?

Select an inspection plan that uses the same strategy as the testing
schedule. You can use the function "Select Inspection Plan" to do this.
When you use this function, you can also see the packages assigned to
the inspection operations in the inspection plans.


Procedure for System Administrators

The system issues an error message and will not allow you to continue with this transaction until the error is resolved.


Error message extract from SAP system. Copyright SAP SE.