Resource assignments to group of activities & not supported
Message type: E = Error
Message class: PJ - MPX interface messages (Download and Upload)
Message number: 730
Message text: Resource assignments to group of activities & not supported
What causes this issue?
You have assigned resources to collective activities in Microsoft
Project (R). The SAP Project System does not recognize collective
activities.
System Response
The resource assignment to collective activites will be ignored during
upload.
How to fix this error?
Collective activities are only used during upload to assign activities
to standard networks.
Error message extract from SAP system. Copyright SAP SE.