For PO & & confirmation/acknowledgment date is & & days too late
Message type: E = Error
Message class: ME - Purchasing: General Messages
Message number: 792
Message text: For PO & & confirmation/acknowledgment date is & & days too late
What causes this issue?
The supplier confirms the date &V3& for purchase order &V1& &V2&.
This date represents a variance of plus &V4& days in comparison with
delivery date in the purchase order: the tolerance limit for too-late
delivery is thus exceeded.
How to fix this error?
Either change the tolerance limit for too-late deliveries (confirmation
sequence) using the Customizing facility:
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
<DS:SIMG.SIMG_CFMENUOLMEOMGZ>Set up confirmation control</>Or change the delivery date in the purchase order:
<DS:TRAN.ME22N>Change purchase order</>
Or get the supplier to change the date in the IDoc.
Error message extract from SAP system. Copyright SAP SE.