Relevance to MRP set at 3, as order released or activated
Message type: E = Error
Message class: IW - Order Processing
Message number: 295
Message text: Relevance to MRP set at 3, as order released or activated
What causes this issue?
You have set the relevancy for materials planning manually to <LB>2</>
(this means "later, or on release").
The order has either already been released or the relevancy for
materials planning for the whole order is on <LB>3</> (this means
"immediately relevant for materials planning").
System Response
The system sets the relevancy for materials planning to <LB>3</>.
How to fix this error?
If you want the component to be considered immediately for
procurement/materials planning, leave the indicator on <LB>3</>.
Otherwise, set the indicator manually to <LB>1</>.
Procedure for System Administrators
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
Error message extract from SAP system. Copyright SAP SE.