Account &1 isn't assigned to semantic tag &2.

Message type: E = Error

Message class: FCO_AVC_PS - Availability Control: Project System

Message number: 220

Message text: Account &1 isn't assigned to semantic tag &2.



What causes this issue?

You have imported a budget for account &v1&. However, account &v1& isn?t
assigned to semantic tag &v2&. Therefore, budget availability control
cannot be used for this account.


System Response

The system responds with a warning but accepts the import.


How to fix this error?

If you want to use budget availability control for account &v1&, you
must assign it to semantic tag &v2&.


Procedure for System Administrators

The system issues an error message and will not allow you to continue with this transaction until the error is resolved.