Cost center &1 references cost center &2, which isn't budget-carrying.
Message type: E = Error
Message class: FCO_AVC_CC - Availability Control: Cost Centers
Message number: 011
Message text: Cost center &1 references cost center &2, which isn't budget-carrying.
What causes this issue?
Cost center &V2& is specified as the budget-carrying cost center for
cost center &V1&. However, cost center &V2& is not budget-carrying for
the period from &V3& to &V4&.
System Response
The system issues an error message and will not allow you to continue with this transaction until the error is resolved.
How to fix this error?
You can specify cost center &V2& as the budget-carrying cost center for
itself. To do this, enter &V2& in the budget-carrying cost center field
for cost center &V2&.
Procedure for System Administrators
Error message extract from SAP system. Copyright SAP SE.
Related Error Messages
FCO_AVC_CC010 Cost center &1 doesn't exist. Select an existing cost center.
FCO_AVC_CC009 Cannot delete budget-carrying cost center &1.
FCO_AVC_CC012 Chart of accounts hierarchy differs for cost center &1 and profile.
FCO_AVC_CC013 Tolerance limit of &2% for cost center &1 has been reached in FY &3.