Planned order & was rescheduled using the next production version

Message type: E = Error

Message class: CY - Capacity Requirements Planning

Message number: 443

Message text: Planned order & was rescheduled using the next production version



What causes this issue?

The system could not dispatch the planned order to the production line
originally intended for it. A possible cause is, for example, a
capacity overload on this line.


System Response

Since you have activated the indicator <ls>Error handling when changing
production version</> the planned order was scheduled for the
production line entered for the production version that is next
alphanumerically.
However, the operation has not yet been dispatched.


How to fix this error?

Dispatch all the rescheduled operations in the planned orders to the
new production lines.