Release date item &1 activity &2 is &3 days in the past

Message type: E = Error

Message class: CN - Meldungen für Netzpläne

Message number: 682

Message text: Release date item &1 activity &2 is &3 days in the past



What causes this issue?

You have triggered the creation of a purchase requisition. The system
determines the release date as the difference between the delivery date
and the total derived from the planned delivery time, the goods receipt
processing time, and the processing time in Purchasing.


System Response

The release date is in the past. Since it is not possible for the
release to be earlier than the current date, the system assigns the
current date to the release date.


How to fix this error?

Check the relevant data for the delivery date and the release date.

Error message extract from SAP system. Copyright SAP SE.