Multiple allocations are not allowed in the std. seq. or parallel seq.

Message type: E = Error

Message class: CM - Task list messages: Material component allocations

Message number: 115

Message text: Multiple allocations are not allowed in the std. seq. or parallel seq.



What causes this issue?

You have carried out one of the following actions:
You checked consistency of component allocation in the routing. The BOM
item is allocated to more than one operation in the standard sequence or
parallel sequence.
You attempted to allocate a BOM item already allocated to an operation
in the standard sequence or parallel sequence.
Neither action is valid because a BOM item can be allocated to only one
operation in a routing. However, allocation of a BOM item to an
operation in an alternative sequence is the only exception.


How to fix this error?

First remove incorrect allocation(s) and then make the appropriate
allocation.